Prescribed Painting or Powder Coating of Parts, Equipment and Apparatus用于部件,設(shè)備及儀器的指定涂料或粉末涂料
1.   Prior to the application of prescribed painting or powder coating, all surfaces to be painted or powder coated should be cleaned and treated in accordance with Instruction D.1.在使用指定的涂料或粉末涂料之前,都應(yīng)該根據(jù)說明D.1的要求,對所有的表面清潔并加以處理。
2.   Assembled sheet metal signal enclosures, battery cases, boxes and other sheet metal structures for outdoor installation should be painted or powder
coated as follows: 安裝好的鈑金信號外殼,電池盒,箱及其它用于戶外安裝的鈑金結(jié)構(gòu)都必須遵照以下要求進(jìn)行涂漆或粉末涂裝:
1.   Prior to the application of prescribed painting or powder coating, all
surfaces to be painted or powder coated should be cleaned and treated in
accordance with Instruction D.1.在使用指定的涂料或粉末涂料之前,都應(yīng)該根據(jù)說明D.1的要求,對所有的表面清潔并加以處理。
2.   Assembled sheet metal signal enclosures, battery cases, boxes and other sheet metal structures for outdoor installation should be painted or powder
coated as follows: 安裝好的鈑金信號外殼,電池盒,箱及其它用于戶外安裝的鈑金結(jié)構(gòu)都必須遵照以下要求進(jìn)行涂漆或粉末涂裝:
© 2010 AREMA
AREMA® C&S Manual
Part 1.5.10                                                                 2010
a.   Painted exterior surfaces should be given one coat of primer, followed by one coat of aluminum paint.  A second coat of finishing
paint, color as instructed, should be applied after erection in the
field.  Powder coated exterior surfaces should be coated with
outdoor powder. 涂漆的外表面應(yīng)先涂上一層底漆,然后再涂上一層鋁粉漆,F(xiàn)場調(diào)試結(jié)束后,根據(jù)顏色要求涂上第二層拋光漆。需進(jìn)行粉末涂裝的外表面應(yīng)使用戶外粉末涂料進(jìn)行涂裝。
b.   Painted interior surfaces should be given one coat of primer,
followed by two coats of finishing paint.  Powder coated interior
surfaces should be coated with indoor powder. 涂漆內(nèi)表面應(yīng)先涂上一層底漆,然后再涂上兩層拋光漆。需進(jìn)行粉末涂裝的內(nèi)表面應(yīng)使用室內(nèi)粉末涂料涂裝。

3.   Knocked-down sheet metal signal enclosures for field assembly should be
painted or powder coated as follows: 應(yīng)該根據(jù)以下幾點(diǎn)對現(xiàn)場組裝的“擊倒”鈑金信號外殼進(jìn)行涂裝或粉末涂料涂裝:
a.   Painted exterior surfaces of all sheet metal panels should be given
one coat of primer.   Powder coated exterior surfaces should be
coated with outdoor powder.所有需要涂裝的鈑金面板表面都必須涂上一層底漆。粉末涂裝的外表面應(yīng)使用戶外粉末涂料涂裝。
b.   Painted interior surfaces of all sheet metal panels should be given one coat of primer, and one coat of finishing paint. Powder coated
interior surfaces should be coated with indoor powder. 所有需要涂裝的鈑金面板表面都必須涂上一層底漆,以及一層拋光漆。粉末涂料涂裝的內(nèi)表面應(yīng)使用室內(nèi)粉末涂料涂裝。
c.   Structural steel parts, such as sill, plate and floor angles, roof trusses and keyhole supports, should be painted with one coat of
primer and one coat of finishing paint or powder coated with indoor
powder.結(jié)構(gòu)鋼部件,如:梁,鋼板和地面角,屋架及鎖孔架都應(yīng)涂上一層底漆及一層拋光漆或使用室內(nèi)粉末涂料進(jìn)行涂裝。
d.   Floor channels, ventilator assembly, and battens, if used, should be
given one coat of primer on all surfaces before shipment. Surfaces
of the floor channels and ventilator that will be exposed inside the
signal enclosure should be given one coat of finishing paint or
powder coated with indoor powder.如有使用,在裝運(yùn)前對所有地面通道,通風(fēng)機(jī)組裝,及綴板表面涂上一層底漆。地面通道及曝露在信號盒內(nèi)的通風(fēng)機(jī)表面需涂上一層拋光漆或用室內(nèi)粉末涂料涂裝。
e.   During assembly and erection in the field, the undersurfaces of floor
channels and understructure of the signal enclosure which will be
exposed to severe atmospheric conditions and which will be
inaccessible after erection, shall be coated with moisture-resistant
compound. 
f.  
Before assembly in the field, battens, if used, should be filled with
caulking compound and, after assembly excess compound should
be wiped off before painting.
g.   After assembly and erection in the field the signal enclosure should
be painted as follows:
2010                                                                  Part 1.5.10
Exterior surfaces should be given two coats of finishing
paint, color as instructed. 使用兩層拋光漆涂,將其顏色作為外部表面的指導(dǎo)樣本。
Interior surfaces should be given one coat of finishing paint,
color as instructed. 給出一層拋光漆涂,將其顏色作為內(nèi)部表面的指導(dǎo)樣本。
4.   Sheet metal cabinets, chaseways, interlocking and control machine cabinets and cases for indoor installation should have exterior and interior
surfaces painted or powder coated in accordance with purchaser’s
instructions. 用于室內(nèi)安裝的金屬薄板箱,大通路包裝材料,聯(lián)鎖和控制機(jī)柜及容器都應(yīng)根據(jù)購買方的要求對外部和內(nèi)部表面進(jìn)行涂漆或粉末涂層。
5.   Metal hoods and backgrounds of signals employing lights should be given one coat of primer, followed by one coat of non-reflecting black coating material. The black finish shall have a specular gloss reading, at 60º, not exceeding 4.0 when measured per American Society for Testing and
Materials test method ASTM Standard D523-08 Standard Test Method for
Specular Gloss.金屬罩和采用燈的信號背景應(yīng)該有一層底漆,其色彩遵照非凡光黑色涂層材料的顏色。黑色面漆的鏡面光澤閱讀必須達(dá)到60º,當(dāng)按照用美國材料與試驗(yàn)協(xié)會標(biāo)準(zhǔn)D523-08 鏡面光澤試驗(yàn)方測量時(shí),不得超過4.0。
6.   Sheet metal targets, signal blades, signs, etc., should be given one coat of
enamel primer, followed by one coat of target enamel, color as instructed.鈑金對象,信號刀片,標(biāo)志等都應(yīng)該有一層搪瓷底漆,顏色根據(jù)目標(biāo)搪瓷涂層而定。
7.   Structural steel and iron parts, such as signal masts, bridges, ladders, platforms and castings such as pole bases, pinnacles and cross-arms for
highway-rail grade crossing signals, etc., should be given one coat of primer. Two coats of finishing paint, color as instructed, should be applied
in the field. One coat of the finishing paint should be applied before and
the other coat after assembly and erection.結(jié)構(gòu)鋼與鑄鐵件,例如:信號桅桿,橋,梯子,平臺以及鑄件,如:桿底,
8.   Steel pipe for signal masts and cable posts should be painted as follows:對信號桅桿,電纜柱的涂裝應(yīng)符合以下幾點(diǎn):
a.   Interior and exterior surfaces of pipe should be given one coat of
primer.管材的內(nèi)外表面都應(yīng)有一層底漆。
b.   Exterior surface of pipe should be given two coats of finishing paint in the field, color as instructed. One coat of the finishing paint
should be applied before and the other coat after assembly and
erection.現(xiàn)場對管材的外表面涂兩層拋光漆,且顏色要符合要求。安裝與調(diào)試結(jié)束后,先涂上一層拋光漆,然后再涂上另一層拋光漆。
9.   Iron and steel castings such as switch machine, circuit controller and spring switch lock cases; signal mechanism and signal enclosures; cases
for train control equipment; motor frames and housing, switch stands, etc.,
(except machine-finished surfaces) should be painted as follows: 鋼鐵鑄件,如:轉(zhuǎn)轍機(jī),電路控制器及彈簧開關(guān)鎖箱;信號機(jī)制和信號盒;列車控制設(shè)備機(jī)箱;電機(jī)框架及外殼,開關(guān)站等(機(jī)器精加工的表面除外)應(yīng)按照如下要求涂裝:
AREMA® C&S Manual
Part 1.5.10                                                                  2010
a.   Exterior and interior surfaces should be given one coat of primer, followed by one coat of finishing paint, color to be purchaser’s
standard.內(nèi)外表面涂上一層底漆,然后再涂上一層拋光漆,顏色要符合購買者的要求。
b.   A second coat of finishing paint, color as instructed, should be applied to the exterior surface after assembly and installation in the
field. 現(xiàn)場組裝與安裝后,根據(jù)要求對內(nèi)表面進(jìn)行二次涂漆。
10.   Black iron pipe and galvanized iron pipe, after being in service, forgings, bars, rods and bolts, such as car retarder and switch machine parts, etc.,
(except machine-finished surfaces) should be painted as follows:黑色鐵管和鍍鋅鐵管,鍛件,棍,棒及螺釘,例如:車輛減速器和轉(zhuǎn)轍機(jī)部件等(轉(zhuǎn)轍機(jī)拋光表面除外),都必須按照如下要求涂裝:
a.   One coat of primer, followed by one coat of finishing paint, color to
be purchaser's standard. 涂上一層底漆,而后再涂上一層拋光漆,顏色符合購買者要求。
b.   A second coat of finishing paint, color as instructed, should be applied after assembly and installation in the field. 在現(xiàn)場,組裝與安裝結(jié)束后按照要求進(jìn)行二次拋光涂裝。
11.   Signal pipe, after installation, should have the joints painted with aluminum paint, to cover exposed threads and wrench marks.安裝完畢后,信號管的接頭必須用鋁粉漆涂裝,已覆蓋外露的線程和扳手痕跡。